Meander

Size:1975KW
Type:Double Runner Francis
Location:Tasmania, Australia
Date:Completed February 2008

Project Scope:

Design, manufacture, supply, install and commissioning of a double runner Francis turbine and control system.  The inlet valve and hydraulic system were also included. Generator 2100kW, Horizontal Induction 6.6kV.